Tower Crane Dismantling Method Statement -

Identification of the qualified personnel involved, such as the Appointed Person, the lift supervisor, and the specialized dismantling technicians. 2. Planning and Regulatory Compliance

Safety harnesses (with double lanyards), hard hats, hi-vis vests, and steel-toed boots. 5. Step-by-Step Dismantling Procedure Phase 1: Preparation

The assist crane supports the counter-jib while pins are removed. The tower head (apex) is disconnected and lowered. Phase 5: Mast Section Removal

Conduct a comprehensive safety hazard assessment of the affected work area to identify potential hazards and appropriate safety measures. The controlling entity must ensure that tower crane foundations and structural supports are in proper condition before dismantling begins. Assess site and ground bearing conditions to ensure they can support both the crane during disassembly and any auxiliary equipment. tower crane dismantling method statement

Certified wire rope slings, web slings, shackles, and spreader beams with valid third-party test certificates. 3.2 Tools & Personal Protective Equipment (PPE) Impact wrenches, torque wrenches, and pinning hammers. Taglines (minimum two 20-meter nylon ropes).

Take the tension on the mobile crane, remove the retaining pins, and lower the counterweight block to the ground.

Understanding the Tower Crane Dismantling Method Statement Dismantling a tower crane is a complex engineering operation that requires meticulous planning and coordination. Unlike the initial assembly, dismantling often takes place once a project is nearing completion, which means the crane may be surrounded by finished structures, active utilities, or public infrastructure. Identification of the qualified personnel involved, such as

No loose tools permitted at height. All hand tools must be tethered to the worker’s harness. Exclusion zones must be enforced below.

Responsible for the overall planning, risk assessment, and preparation of the method statement. They hold ultimate authority over the operation.

A physical barrier at ground level to prevent unauthorized entry into the "drop zone." Phase 5: Mast Section Removal Conduct a comprehensive

Attach the mobile crane rigging to the designated lifting lugs on the main jib. The rigging must match the center of gravity (CoG) specified in the manual.

[Preparation & Positioning] │ ▼ [Telescoping Down (If Applicable)] │ ▼ [Counter-Weight Removal (Partial)] │ ▼ [Jib Removal & Lowering] │ ▼ [Remaining Counter-Weights Removal] │ ▼ [Counter-Jib Removal] │ ▼ [Tower Top / Apex Removal] │ ▼ [Slewing Ring & Cabin Removal] │ ▼ [Mast Section & Base Dismantling] Step 5.1: Telescoping Down (For High-Rise Cranes)

Only the slewing power should remain active to facilitate rotation of the upper structure during dismantling, if required.

: Identification of hazards such as falls from height, falling objects, and mechanical failure. Communication Plan

Workers must wear full-body harnesses with dual lanyards, hooked 100% of the time to certified anchor points or temporary lifelines.